PGESCO

Al Shabab Desalination and Water Treatment Facilities

project details

Al Shabab Desalination and Water Treatment Facilities

Region: Egypt Status: Completed

PLANT DESCRIPTION

Al Shabab power project includes desalination and water/wastewater treatment systems to serve the plant water demand of high purity demineralized water required for boiler feed as well the various power plant users. Ground Water is supplied via deep well field to feed the desalination and water treatment systems.

PGESCO scope is Full EPCM services for the whole power plant including complete water treatment facilities, the scope covers engineering, procurement, project and construction management.

Project Details

Owner

East Delta Electricity Production Company

Location

Egypt, Ismailia

Date of Award

October 2011

Scope

Engineering Consultancy Services.
Engineering, Procurement, and Construction Management Services.

Related Project

Water Solutions

West Damietta Simple Cycle Fast Track Power Project

By: East Delta Electricity Production Company Date: 2005

Water Solutions

Sidi Krir Combined Cycle Power Project

By: West Delta Electricity Production Company Date: 2003

Water Solutions

Al Atf Combined Cycle Power Project

By: West Delta Electricity Production Company Date: 2003

Water Solutions

Banha Combined Cycle Power Project

By: Cairo Electricity Production Company Date: 2003

Water Solutions

Giza North Combined Cycle Power Project

By: Cairo Electricity Production Company Date: 2003

Water Solutions

West Damietta Simple Cycle Power Project

By: East Delta Electricity Production Company Date: 2005

Water Solutions

Suez Thermal Power Project

By: East Delta Electricity Production Company Date: 2005

Water Solutions

Cairo West Thermal Power Project

By: Cairo Electricity Production Company Date: 2003

Water Solutions

Al Tebbin Thermal Power Project

By: Cairo Electricity Production Company Date: 2003

Water Solutions

El Kuriemat Combined Cycle Power Project

By: Upper Egypt Electricity Production Company Date: 2003

Water Solutions

Talkha Combined Cycle Power Project

By: East Delta Electricity Production Company Date: 2003

Water Solutions

Nubaria Combined Cycle Power Project

By: West Delta Electricity Production Company Date: 2003

Water Solutions

Cairo North Combined Cycle Power Project

By: Cairo Electricity Production company (CEPC) Date: 2003

Water Solutions

SOUTH HELWAN Water Treatment Systems

By: Upper Egypt Electricity Production company Date: 2003

Water Solutions

NEW CAPITAL Water Treatment Systems

By: ORASCOM CONSTRUCTION Date: 2015

Water Solutions

New Assiut Water Treatment Facilities

By: Upper Egypt Electricity Production Company (UEEPC) Date: 2014

Water Solutions

New West Damietta Desalination and Water Treatment Facilities- Fast Track

By: East Delta Electricity Production Company Date: 2014

Water Solutions

Sidi Krir Desalination and Water Treatment Facilities

By: West Delta Electricity Production Company Date: 1996

Water Solutions

Ayoun Mousa Desalination and Water Treatment Facilities

By: East Delta Electricity Production Company Date: 1996

Water Solutions

Abu Qir Desalination and Water Treatment Facilities

By: West Delta Electricity Production company Date: 2009

Water Solutions

El Ain El-Sokhna Desalination and Water Treatment Facilities

By: East Delta Electricity Production Company Date: 2010

Water Solutions

Al Burullus Desalination and Water Treatment Facilities

By: Middle Delta Electricity Production Company Date: 2015

Water Solutions

New Assiut Water Treatment Facilities

By: Upper Egypt electricity Production Company Date: 2018

Water Solutions

New Cairo West Water Treatment Facilities

By: Cairo Electricity Production Company Date: 2018