PGESCO

Obari Power Plant 4 x 160 MW

project details

Obari Power Plant 4 x 160 MW

Region: Libya Status: On Going

PLANT DESCRIPTION

Design review, site supervision and project management of Obari 4 X 160 MW 
(crude oil fired) project. 

The scope also included plant equipment material inspection and  
performance testing.  

Project Details

Owner

General Authority of Electricity and Renewable Energy of Libya

Client

ACESCo/GAEREL

Location

Libya, Southwest of Libya

Date of Award

January 2010

Scope

Contract for Engineering, Procurement, Project, and Construction Management Services.

Related Project

Power Projects

Sarir Power Plant 3 X 285 MW

By: General Authority of Electricity and Renewable Energy of Libya Date: 2007

Power Projects

Western Mountain Extension Power Plant 2 X 156 MW

By: General Authority of Electricity and Renewable Energy of Libya Date: 2007

Power Projects

Western Mountain Power Plant 4 x 156 MW

By: General Authority of Electricity and Renewable Energy of Libya Date: 2003

Power Projects

Zawia Power Plant 2 x 150 MW

By: General Authority of Electricity and Renewable Energy of Libya Date: 2004

Power Projects

ZWITINA 570 MW SIMPLE CYCLE

By: General Electricity Company of Libya Date: 2011

Power Projects

Lamlouda Power Plant 3x50 MW-Simple Cycle

By: USP LY / Ras Al Khaimah United Arab Date: 2017

Power Projects

Zwitina Power Plant Add-on 250 MW

By: General Electricity Company of Libya Date: 2010

Power Projects

Misrata Power Plant 750 MW

By: ACESCO - GAEREL Date: 2007

Power Projects

Susa 3x300 MW Power Project

By: USPE-LY / Ras Al Khaimah United Arab Emirates Date: 2018

Power Projects

Benghazi West 2000 MW

By: General Electricity Company of Libya Date: 2018