PGESCO

Nubaria (1) & (2)

project details

Nubaria (1) & (2)

Region: Egypt Status: Completed

1) Nubaria (1)&(2) 500 kV

Equipment Type/Rating:

  • 500 kV AIS (Hitachi Power Systems), Busbar rating: 500 kV, 3000 A, 40 kA, 1sec, Breaker rating: 2000 A
  • 3 x 500/220 kV Tie Transformers (manufactured by ZTR)

Configuration:

11 Bays, Double Busbar-Double Breaker

2) Cairo 500 kV AIS extension

Equipment Type/Rating:

  • 500 kV AIS, Busbar rating: 500 kV, 3000 A, 40 kA, 1sec, Breaker rating: 2000 A

Configuration:

Single Bay, Double Busbar, Double Breaker

3) Nubaria (1)&(2) 220 kV

Equipment Type/Rating:

  • 220 kV AIS (ABB), Busbar rating: 245 kV, 3000 A, 40 kA, 1sec, Breaker rating: 1600 A

Configuration:

12 Bays Double Busbar-Single Breaker and one Bus-Tie

Project Details

Owner

Middle Delta Electricity Production Company

Location

Egypt, Alexandria

Date of Award

September 2003

Scope

Project management, construction management, startup and commissioning management, which included initial operation support.

Related Project