6 October 220 kV Phase (1)

Region: Egypt Status: Completed

Equipment Type/Rating:
220 kV GIS (ABB Type ELK-14/300), Busbar rating: 245 kV, 2500 A, 50 kA, 1sec, Breaker rating: 2000 A
Configuration:
4 Diameters, Breaker and a half

 

Project Details

Owner

Cairo Electricity Production Company

Location

Egypt, Giza

Date of Award

February 2011

Scope

CM, PMC including start up management services as well as O&M services including training management.

Related Project

Subsations

New West Damietta 220 kV Switchyard Extension

By: East Delta Electricity Production Co. Date: 2014

Subsations

New Assiut 220 kV Switchyard Extension

By: Upper Egypt Electricity Production Co. Date: 2016

Subsations

West Damietta 220 kV Switchyard Extension

By: East Delta Electricity Production Co. Date: 2015

Subsations

Shabab 220 kV switchyard Extension

By: East Delta Electricity Production Co. Date: 2015

Subsations

South Helwan 500 kV

By: Upper Egypt Electricity Production Co. Date: 2015

Subsations

New West Damietta 220 kV

By: East Delta Electricity Production Company Date: 2015

Subsations

New Assiut 220 kV

By: Upper Egypt Electricity Production Company Date: 2015

Subsations

Suez 500 kV

By: East Delta Electricity Production Company Date: 2010

Subsations

6 October 220 kV Phase (2)

By: Cairo Electricity Production Company Date: 2013

Subsations

Giza North

By: Cairo Electricity Production Company Date: 2011

Subsations

Banha 220 kV

By: Middle Delta Electricity Production Company Date: 2010

Subsations

Ain El Sokhna 500 kV

By: East Delta Electricity Production Company Date: 2010

Subsations

West Damietta

By: East Delta Electricity Production Company Date: 2011

Subsations

Shabab 220 kV

By: East Delta Electricity Production Company Date: 2010

Subsations

Damietta 220 kV

By: East Delta Electricity Production Company Date: 2010

Subsations

Abu Qir 500 kV

By: West Delta Electricity Production Company Date: 2009

Subsations

Cairo West 500 kV Extension

By: Cairo Electricity Production Company Date: 2008

Subsations

Sidi Krir (5) & (6) 500 kV GIS Extension

By: West Delta Electricity Production Company Date: 2005

Subsations

El Atf 220 kV

By: Middle Delta Electricity Production Co. Date: 2007

Subsations

Tebbin 220 kV

By: Cairo Electricity Production Company Date: 2007

Subsations

Kureimat 220 kV

By: Upper Egypt Electricity Production Company Date: 2005

Subsations

Nubaria (3) 500 kV

By: Middle Delta Electricity Production Company Date: 2007

Subsations

Nubaria (1) & (2)

By: Middle Delta Electricity Production Company Date: 2003

Subsations

Cairo North 220 kV

By: Cairo Electricity Production Company Date: 2003

Subsations

Ayoun Mousa

By: East Delta Electricity Production Company Date: 1996

Subsations

Sidi Krir 220 kV

By: West Delta Electricity Production Co. Date: 1996

Subsations

Southeast Coast Overhead Transmission Line & Substations

By: Egyptian Electricity Transmission Company Date: 2019

Subsations

Toshka Substation and Related Transmission Line Project

By: Egyptian Electricity Transmission Company Date: 2019

Subsations

Naga Hamady 500/220/66/11 kV GIS

By: Egyptian Electricity Transmission Company Date: 2018

Subsations

East Qena 500/220/66/22kV GIS

By: Egyptian Electricity Transmission Company Date: 2018

Subsations

Project Consulting Service for Cairo Regional Control Center upgrade Project “CRCC”

By: Egyptian Electricity Transmission Company Date: 2019

Subsations

Zahraa Nasr City 220/66/11 KV GIS

By: Egyptian Electricity Transmission Company Date: 2020

Subsations

El Eqtsadiya (2) 500/220/66/22 KV GIS

By: Egyptian Electricity Transmission Company Date: 2020