East Qena 500/220/66/22kV GIS substations consist of the following: -
-9 Bays 500 KV GIS
-14 Bays 220 KV GIS,
-8 Bays 66 KV AIS,
-22 Cells 22 KV MVSG,
Power Transformers
-500/220 KV 3*175 MVA TR.,
-220/66 KV 3*175 MVA TR.,
-66/11 KV 4*40 MVA TR.
PGESCO scope is Detailed Engineering and issuing Material Requisitions for the balance of the substation equipment excluding Major Equipment for the Substation.
Project Details
Owner
Egyptian Electricity Transmission Company
Client
XD-EGEMAC
Location
Egypt, Qena
Date of Award
October 2018
Scope
Engineering and issuing Material Requisitions for the balance of the substation equipment excluding Major Equipment for the Substation.