Preparing a tender and invite interested tenderers to execute a limited operation for replacing the porcelain insulators with rubber insulators of MidElec 66kV OHTLs (M1, M2 & M3) and applying RTV protective coatings as needed.
The outline of the intended work will include the listed below activities:
Phase 1 (11 weeks)
- Surveys (for Site and Market)
- Tender Preparation including General, Special Conditions and technical requirements.
- Invitation to Tenderers
- Receiving/Responding to Tenderer Clarifications (if any)
- Receiving offers and Evaluation
- Recommendation Report, preparation of final Contract and issuance draft LOA.
- Following-up the insulators’ manufacturing and attending factory testing if required and notifying Midelec that the insulators are ready to be used for phase 2 (Construction and installation phase).
Phase 2 ( First quarter of 2021)
- Construction & installation supervision and management.