PGESCO

MIDELEC Insulators Replacement Study

MIDELEC Insulators Replacement Study

Project 
 
MIDELEC Insulators Replacement Study
 
Client 
 
MIDOR Electricity Co.
 
Date
 
September 2020
 
Location 
 
Alexandria

Scope

Engineering Studies Services.

Preparing a tender and invite interested tenderers to execute a limited operation for replacing the porcelain insulators with rubber insulators of MidElec 66kV OHTLs (M1, M2 & M3) and applying RTV protective coatings as needed.
 
The outline of the intended work will include the listed below activities:
 
Phase 1 (11 weeks)
  1. Surveys (for Site and Market)
  2. Tender Preparation including General, Special Conditions and technical requirements.
  3. Invitation to Tenderers
  4. Receiving/Responding to Tenderer Clarifications (if any)
  5. Receiving offers and Evaluation 
  6. Recommendation Report, preparation of final Contract and issuance draft LOA. 
  7. Following-up the insulators’ manufacturing and attending factory testing if required and notifying Midelec that the insulators are ready to be used for phase 2 (Construction and installation phase).
 
Phase 2 ( First quarter of 2021)
  1. Construction & installation supervision and management.