Device Study Project

Device Study Project

Project 

Device Study Project

Client 

Midor Electricity Co. “MIDELEC”

Location

Alexandria, Egypt

Scope

PGESCo to Study the Well-Timed Decoupling and Following Load Shedding to Ensure Continued Operation Following Faults and to Avoid the Total Loss of The Refinery, The Scope of Work Includes the Following Activities as Following:

  • Data Collection 
  • ETAP Modeling for The Electrical Network Considering National Electrical Network Interconnection
  • Data Verification
  • Load Flow Analysis
  • Transient Stability Study 
  • Decoupling Device and Load Shedding Study 
  • Decoupling Device Setting