1) Nubaria (1)&(2) 500 kV

Equipment Type/Rating:

  • 500 kV AIS (Hitachi Power Systems), Busbar rating: 500 kV, 3000 A, 40 kA, 1sec, Breaker rating: 2000 A
  • 3 x 500/220 kV Tie Transformers (manufactured by ZTR)

Configuration:

11 Bays, Double Busbar-Double Breaker

2) Cairo 500 kV AIS extension

Equipment Type/Rating:

  • 500 kV AIS, Busbar rating: 500 kV, 3000 A, 40 kA, 1sec, Breaker rating: 2000 A

Configuration:

Single Bay, Double Busbar, Double Breaker

3) Nubaria (1)&(2) 220 kV

Equipment Type/Rating:

  • 220 kV AIS (ABB), Busbar rating: 245 kV, 3000 A, 40 kA, 1sec, Breaker rating: 1600 A

Configuration:

12 Bays Double Busbar-Single Breaker and one Bus-Tie

Project Details

Owner

Middle Delta Electricity Production Company

Location

Egypt , Alexandria

Date of Award

September 2003

Scope

Project management, construction management, startup and commissioning management, which included initial operation support.