PGESCO

500 kV Overhead Transmission Line - Project ( Benban III - Toshka II-500 KV OHTL- 255 Km)

project details

500 kV Overhead Transmission Line - Project ( Benban III - Toshka II-500 KV OHTL- 255 Km)

Region: Egypt Status: Completed

PLANT DESCRIPTION

255 Km, Benban III – Toshka II -500 KV OHTL - double-circuit, triple -bundle conductor, divided in three lots each 85 KM average.

PGESCO scope is full PMC and CM services including design review, equipment, and material inspection. 

Project Details

Owner

Egyptian Electricity Transmission Company

Location

Egypt, Aswan

Date of Award

December 2019

Scope

Project and Site Management Supervision Including Design Review, Equipment, and Material Inspection.

Related Project

Over Head Transmission

±200MVar STATCOM System 220kV Substation

By: Egyptian Electricity Transmission Company Date: 2021

Over Head Transmission

500 kV OHTL - Project (Sidi Krir- Nubaria- Cairo)

By: Egyptian Electricity Transmission Company

Over Head Transmission

El Quseir/Marsa Alam/Bernes 220 kV OHTL- 300 Km

By: Egyptian Electricity Transmission Company

Over Head Transmission

Benban III – Nagaa Hamadi-500 kV OHTL- 195 Km

By: Egyptian Electricity Transmission Company