PGESCO

1000KM 400 kV OHTL

project details

1000KM 400 kV OHTL

Region: Libya Status: Completed

Scope

Design Review, Site Supervision And Project Management of The Project. The Scope Also Included Plant Equipment, Material Inspection And Performance Testing As Well As Training And Technology Transfer To GPCOEWG (General People’s Committee of Electricity, Water and Gas).

The Project Consists of Two (2) 400kV Overhead Transmission Lines With Total Length of 1000 Km.

The First Line Is Zawia-Sidi Banour (500 Km) And The Second Line Is Sirt -Agdabia (500km).

Project Details

Owner

ACESCo/GAEREL

Location

Libya, Zawia-Sidi Banour / Sirt -Agdabia

Date of Award

January 2008

Related Project

Over Head Transmission

Sabha Gamra 400 kV OHTL

By: ACESCo/GAEREL Date: 2014

Over Head Transmission

Rwes – Bir Ganam 220 kV OHTL

By: ACESCo/GAEREL Date: 2014

Over Head Transmission

Brak – Sabha 220 kV OHTL

By: ACESCo/GAEREL Date: 2014

Over Head Transmission

1000 KM 400 kV OHTL

By: General Electricity Company of Libya (GECOL) Date: 2014